*Crews from A&I Environmental Services Inc, along with Advanced Air Analysis Inc continue to have a daily presence in the neighborhood.
*To date, 900 mailers have been sent to residents (three separate mailings)
300 flyers have been distributed door-to-door.
*Signage, approved by Councilman Torrence has been displayed in the park as requested at the last meeting.
*Ongoing communication continues between TTI and MDE.
*The tower has been being inspected, any loose chips found vacuumed as required and then the tower is de-rigged.
*The tower inspection for loose paint has been completed. No loose chips were found, and the tower has been de-rigged. Skyline has removed all equipment from the facility and has left the property.
*TTI continues to urge residents to reach out to the e-mail address provided if there is a need for further mitigation. Residents should communicate cleanup requests to TTI by email at televisiontowerinc@gmail.com or by phone at 410-578-7551